Successful location and stabilisation of a leak path in the completion string

Posted by Peak Well Systems on 04-Oct-2016 08:00:00
Find me on:

CS20-Successful_location__stabilisation.jpg

An International Oil Producer with operations in Africa encountered wellbore leakage issues within the completion string in one of their offshore wells.

Peak provided an efficient and effective rig-less solution utilising the SIM Retrieveable Bridge Plug to isolate and stabilse the leak path whilst ensuring the intervention was carried out safely and with zero downtime.

The Challenge

The Customer sought to confirm the area of pressure communication between the annulus and tubing on the completion string but they could not get to the XN nipple to set an isolation plug and therefore test the strings to determine which string was leaking.

The key objective for the Customer was to locate and fix the leak path and ensure intervention was carried out safely and with zero downtime. The solution had to be cost effective using Peak SIM Retrievable Bridge Plug inventory, owned by the Customer.

 

CS20-quote.jpg

 

Peak’s Solution
Peak worked proficiently with their Nigerian partner to set a 2-7/8" SIM Retrievable Bridge Plug effectively at 8,739ft, with 36 degrees deviation on the long string.

Peak’s SIM Plugs can pass through all standard completions allowing them to be mechanically set anywhere within the completion string, without the need for a nipple profile.

Pressure testing identified the string leakage as annulus to tubing communication higher up the completion.

A second 2-7/8" SIM Retrievable Bridge Plug was set at 8,212ft on the short string and a Back Pressure Valve (BPV) set higher in the long string, to stabilise the leakage and ensure well safe barriers were in place for workover operations.

The SIM Plugs isolated the reservoir effectively and allowed the customer time to evaluate and investigate further options.

 

 

SIM_Plug_Close-up_600x424-1.jpg

 

 

Value to Customer

  • Peak provided an efficient and effective rig-less solution, utilising the Customer-owned SIM Plug inventory. Peak’s SIM Plugs were tested and set first time at depth and 36 degrees deviation
  • Peak was able to isolate the reservoir without complications and ensure regulatory dual pressure barriers were in place, whilst a workover plan was considered

To download a copy of the case study, click the link below:

DOWNLOAD CASE STUDY

If you are encountering similar challenges, we are here to help. Please contact us to speak to one of our Technical Sales Managers to discuss your requirements further.

SPEAK TO AN EXPERT

Product Code(s): SIM Retrievable Bridge Plug - 351; SIM Running Tool - 350

#SIMSystem #PeakWellSystems

Topics: Technical Case Studies, SIM Plugs, Offshore

Improving the performance of wells through advanced downhole technology

Subscribe to our blog for insights into the latest industry technologies and innovations, and learn how we are helping our customers reduce well operating costs and improve well performance.

Subscribe to Email Updates

Recent Posts